試卷名稱 2017年信息系統(tǒng)項(xiàng)目管理師最新英語(yǔ)模擬題(5)
考試中心《2017年信息系統(tǒng)項(xiàng)目管理師最新英語(yǔ)模擬題(5)》在線考試
試卷年份2017年下半年
試題題型【單選題】
試題內(nèi)容

Market dynamics have changed. The project sponsor wants to terminate the project because of its uncertain performance. What should the project manager and the project sponsor review?
A、A root cause analysis and an action plan for the technical issues
B、Project's technical and commercial goals, viability, and Profitability
C、A change request to modify the project requirements
D、Explanations of the process that caused the technical issues