The project has an earned value (EV) of US$1,530, and a planned value (PV) of US$1,630. A team member suggests
removing a   deliverable to benefit the schedule and positive impact the critical path. After documenting the details, the project manager proceeds?
A. Submit a change request
B. Change the project management plan
C. Recalculate the PV
D. Perform a reserve analysis